1.8. Additional documents relevant for the mounting
In addition to these Mounting Instructions, the following documents are required for the mounting of FS Uno:
2. Transportation, Loading and Unloading
2.1. Delivery of the components
The delivery of the components for FS Uno is carried out with an appropriate vehicle, for example
• trucks/lorries or
• overseas containers
2.2. Preparing the delivery
• Provide a stable and drivable surface for the delivery.
• Please make sure that all access roads, manoeuvring and unloading areas are suitable for trucks (up to 40 tons)
and can be used by forklift trucks and hoisting equipments.
• Please exclusively provide trained professionals for the loading and transportation activities.
WARNING
• Always wear protective equipment (safety shoes, hard hat, safety glasses, protective gloves and
reective vest) when unloading the FS Uno components.
• Besides also wear the personal protective equipment that is specied in your intra-company
regulations for the respective activity.
• It is compulsory to monitor and supervise the complete unloading process .
• Do not step under suspended loads!
• Please make sure that there are no unauthorized persons in the danger area.
• Pile-driving plan
• Blueprint drawing / general layout drawing
• Bill of materials / parts list
• Delivery note
• DIS unloading guidelines for transport in maritime containers
• General Terms and Conditions of Sale and Supply of Schletter GmbH
• Data sheet and instructions of the module manufacturer
Please observe all country-specic regulations and standards of the country of destination and its work
instructions!
Schletter Solar GmbH – Alustraße 1 – 83527 Kirchdorf
Mounting instruction FS UNO with SRF Foundation Posts | 2016.09 V.004