Fireplace stove SENKO SP 12
4.2. CHIMNEY PREPARATION AND CONTROL
Before installing the replace stove, it is necessary to check the
chimney - diameter, height, that it is not blocked or damaged. The
chimney must have a certicate from an authorized local chimney
sweep.The eective height of the chimney must be at least 5 meters from
the point of exhaust of ue gases (Figure 5b). The underpressure of the
chimney must be within the limits of 12 ± 2 Pa.
The chimney must be at least 0.5 meters above the ridge of the
roof. The minimum distance between two connections on the same
chimney must be 60 cm (Figure 5d). The diameter of the chimney is
selected according to the chimney manufacturer's data - for example, for
a negative pressure of 12 Pa, it is usually a diameter of 160 mm.
The chimney must be smooth on the inside, well insulated and well
sealed. All cleaning openings must be well sealed. Seals must be
regularly controlled and changed as necessary.
4.3. CONNECTION TO THE CHIMNEY
When connecting the stove to the chimney, it is necessary to comply
with local, national and European regulations (norms) - DIN 4705. Care
must be taken to ensure that the connection between the pipe and the
chimney is tight and leak-proof. The ue pipe must have a suitable
rise in case the stove is far from the chimney opening. The ue pipe
must not enter the bright opening of the chimney (Figure 5c). The
dierences between correct and incorrect connection of the replace
stove to the chimney are shown in the following picture.