INSTALLATION MANUAL
SINCE 1965
E R A I
S
Gate Opener Department
MERCURIO 524A F SR 24.85/24A F KIT WITH ENCODER FOR SLIDING GATES UP TO 500 kg -24Vdc
CAUTION: READ THIS MANUAL CAREFULL
Y BEFORE
MAKING ANY CONNECTIONS,
AND KEEP FOR
FUTURE REFERENCE
MERCURIO 524A H SR 24.84/24A MOTOR WITH CONTROL UNIT FOR SLIDING GATES UP TO 500 kg -24Vdc

Questions and Answers

  • J
    John WilliamsAug 21, 2025
    How to troubleshoot a Serai SR 24.85/24A F gearmotor that is not working?
    • T
      Teresa BrandtAug 21, 2025
      If the Serai Gate Opener gearmotor is not working, check the motor power supply input terminals to see if they are live. Check F4 mains fuse efficiency. Check the 24V presence at the motor power supply clamps 5 and 6. Check that the power supply cable is not cut or broken (cable replacement must be carried out by an authorised technician). Also, check and replace the fuse if it's faulty.
  • S
    Sonia CarpenterAug 30, 2025
    How to fix a Serai SR 24.85/24A F when the gate is jammed against the mechanical end stop?
    • O
      Olivia CoxAug 30, 2025
      If the Serai Gate Opener gate is jammed against the mechanical end stop, remove the lower casing from the motor. Unscrew the nuts fastening the base plate bolts. Remove the motor from its position by releasing the pinion from the tooth rack. By hand, move the gate right away from the mechanical end stop. Release the motor manually. Reposition the motor on the base plate. Set the end stop sliding plates properly. Replace the lower casing and secure the motor. If necessary, repeat the work times and impact force setting programming.
  • J
    Jason GreeneNov 10, 2025
    What to do if the Serai Gate Opener does not complete its travel?
    • P
      Priscilla TapiaNov 10, 2025
      If your Serai Gate Opener does not complete its travel, manually release the gate and check for any obstacles. If you find obstacles, remove them. Then, repeat the “work times and impact force setting programming” procedure, setting a greater force. Note that the impact control can be switched off by positioning the SW1 microswitch 1 to ON; in this case, other safety systems compliant with regulations in force (e.g. sensitive edges) must be adopted. If there was a power cut during operation, the first opening manoeuvre takes place during deceleration (if the gate is in an intermediate position) and can take up to 300 s; if it does not occur within this time, the gate must be moved to the fully open or fully closed position by hand. Also, check and adjust the position of the end stop slidin...