Commissioning with steam or liquid

Pressure transmitter
Shut-off fitting
Shut-off valve to process
Shut-off valve for test connection or for bleed screw
Pressure line
Shut-off valve
Blow-out valve
Compensation vessel (steam only)
Figure 3 Measuring steam
Requirement
All valves are closed.
Procedure
To commission the transmitter for steam or liquid, proceed as follows:
1. Open the shut-off valve for the test connection
.
2. Via the test connection of the shut-off module
, apply the pressure corresponding to the start of scale value to the
pressure transmitter
.
3. Check the start of scale value.
4. If the start of scale value differs from the value desired, correct it.
5. Close the shut-off valve for the test connection
.
6. Open the shut-off valve
at the pressure tapping point.
7. Open the shut-off valve for the process
.