SIMOTION D4x5-2
Commissioning and Hardware Installation Manual, 02/2012
83
Commissioning (hardware)
4
4.1 Requirements for commissioning
Requirements
The following requirements must be satisfied for the initial commissioning of the
SIMOTION D4x5-2 and the SINAMICS S120 modules required for operation
(SINAMICS S120 line modules and SINAMICS S120 motor modules):
Your system with SIMOTION D4x5-2 has been installed and wired.
Your PG/PC has been connected to the SIMOTION D4x5-2 via the PROFIBUS, Ethernet
or PROFINET IO interface.
Commissioning steps
Commissioning the hardware involves the following steps:
1. Inserting the CompactFlash card (Page 84)
2. Checking the system (Page 86)
3. Switching on the power supply (Page 86).
Additional references
For information on installing/mounting and commissioning the SINAMICS S120 components,
refer to the
SINAMICS S120
Commissioning Manual.

Table of Contents

Other manuals for Siemens SIMOTION D445-2

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Siemens SIMOTION D445-2 and is the answer not in the manual?

Siemens SIMOTION D445-2 Specifications

General IconGeneral
BrandSiemens
ModelSIMOTION D445-2
CategoryControl Unit
LanguageEnglish

Related product manuals