DC INVERTER U-MATCH AIR CONDITION MAINTENANCE
169
2. Remove the coil
of electronic
expansion valve
Remove the coil from
electronic expansion
valve.
3. Remove the
electronic
expansion valve
Use gas welding to
heat the pipes connected
on the two ends of
electronic expansion
valve. Then, pull them
out from the electronic
expansion valve.
Weld by charging
nitrogen for protection,
with the nitrogen
pressure kept at
0.5±0.1kgf/c 󱚸 (relative
pressure).During
heating, take care to
prevent the substances
around from burn due to
high temperature.
4. Move the
electronic
expansion valve
away
Remove the old
electronic expansion
valve.