8 | INSTALLATION, OPERATION and MAINTENANCE MANUAL
Further details can be found in Section 7.0: “Receiving of Equipment”.
How to contact SPX FLOW:
Your nearest SPX FLOW office is listed on our website www.spxflow.com.
Information regarding our Service and Spare Parts offerings can also be found on
the website.
3.2. Operating Zone
An operating zone should be established around all heat exchangers. A brightly painted
guard rail or warning stripe should define the zone. Only the operator or other
authorized personnel should be within the operating zone when equipment control
circuits are energized, or the heat exchanger is operating. No tools or other equipment
should be kept within the operating zone.
3.3. Installation
Utilities, such as water, steam, electricity, and pressurized air, should be installed by
trained and authorized personnel only. Installations must comply with all applicable
codes and standards, including those established by OSHA.
3.4. StartUp and Shutdown Instructions
Before Operating a GPHE
a. Ensure all necessary guards and safety devices are installed and operating
correctly. This includes safety screen or pressure relief devices.
b. Be sure all personnel are clear of the GPHE.
c. Remove (from the operating zone) any materials, tools or other foreign objects
that could cause injury to personnel or damage the GPHE.
After Shutdown
Make certain all pressure in the heat exchanger is released.
3.5. General Operating Safety
a. Do not operate this heat exchanger until you read and understand the operating
instructions and become thoroughly familiar with the equipment and its
operation.
b. Never operate a heat exchanger while a safety device or guard is removed or
disconnected.
c. Always wear safety glasses, safety hat, steel-toed shoes, ear protection and
any other required safety equipment.