ENGLISH
WWW.STIEBEL-ELTRON.COM WPL 10 ACS | 9
INSTALLATION
PREPARATIONS
Example: T-support SK-WPL
A
B
2
8
5
7
3
4
1
D0000019236
A Frost level
B 300
1 Heating circuit flow
2 Heating circuit return
3 Conduit for supply lines
4 Foundation
5 T-support
6 Gravel bed
7 Drainage pipe
8 Condensate hose
Observe the static limits of the T-support used.
Example: Wall mounting support WK-WPL
≥200
2
5
3 1
D0000019244
1 Heating circuit flow
2 Heating circuit return
3 Condensate hose
4 Drainage pipe
5 Wall mounting bracket
Observe the static limits of the building wall and the wall
mounting supports.
Example: Foundation slab
610
635
265
525
1350
e01
e02
80
110
b01
120
4
5
1
3
2
D0000034844
b01 Entry electrical cables” from below
e01 Heating circuit flow
e02 Heating circuit return
1 Air intake side
2 Air discharge side
3 Main wind direction
4 Condensate hose
5 Outlet for supply lines
2
8
7
3
4
1
2
1
9
5
A
70-80
D0000024451
A Frost level
1 Heating circuit flow
2 Heating circuit return
3 Conduit for supply lines
4 Foundation
5 Mounting bracket MK-WPL 10 AC(S)
6 Gravel bed
7 Drainage pipe
8 Condensate hose
9 Outlet for supply lines opt.