Strasbaugh Mechanical Maintenance Procedures
Version 4.0 - February 1998 9 - 85
LOAD STATIONS
CENTERING THE LOAD STATIONS
UNDER THE SPINDLES
A. BEFORE YOU BEGIN
Tools Required
• none
Turn Machine Power On and Perform Home Sequence Routine
Follow the procedures detailed in the Operator Functions chapter of the 6DS-SP
Operations manual.
B. CENTER THE LOAD STATIONS UNDER THE SPINDLES
Note: Lowering the spindles and applying a small amount of down force
centers the load stations automatically.
1. Load carriers on the spindles:
• Follow the procedures detailed in the Operator Functions chapter of
the 6DS-SP Operations manual.
2. At Page 1 of the Manual Control Menu, select Bridge Move and choose
Load to move the bridge to the load stations.