FRONTIER
®
FREESTANDING CARPORT
STRATCO FRONTIER ASSEMBLY INSTRUCTIONS.
®
Your complete guide to building a FRONTIER
CARPORTFREESTANDING
®
BEFORE YOU START
Carefully read these instructions. If you do not have all the necessary tools or information, contact Stratco for advice. Lay
out all components and check them against the delivery docket. The component location diagram below identifies each
key part and indicates their fastening positions.
7
5
4
3
2
1
Barge Capping
C-Section
VF Gutter
SHS Posts
Prodek Roofing
®
VF Stop End
Downpipe
6
3
6
4
1
7
5
2
Drill & Hex-Head Adaptor
Rivet Gun
Tape Measure
Tin Snips
Spirit Level
Hack-Saw
Post hole digger
Silicone Gun
Spanners or Ratchet
Adjustable Construction Props
Turn Up/Down Tool
Concrete
Ladder
TOOLS REQUIRED
Question and Answer IconNeed help?

Do you have a question about the Stratco FRONTIER and is the answer not in the manual?

Stratco FRONTIER Specifications

General IconGeneral
BrandStratco
ModelFRONTIER
CategoryToy
LanguageEnglish

Summary

Introduction

Marking Out Carport Position

In Ground Footing

Place stakes at carport post locations, tie string lines for alignment, and dig holes for posts.

On Concrete Footing

Check concrete slab dimensions, mark post positions, and ensure alignment for on-concrete installations.

Assembling the Framework

Pre-Drill Holes

Pre-drill holes in C-Section beams and SHS posts for perimeter beams, and in intermediate beams/purlins.

Posts

Stand posts in footing locations and brace them securely with clamps and struts.

Perimeter Beams

Bolt perimeter beams to posts using M12 bolts and washers, ensuring they are on the inside/outside face of posts.

Intermediate Beams and Purlins

Attach angle brackets to intermediate beams and purlins, then drill and bolt them to adjoining beams.

Footings

In Ground Footing

Concrete the footings and allow them to cure, finishing raised towards the column for water runoff.

On Concrete Footing

Drill holes in the footing plate, then fix plates to the concrete slab using screwbolts.

Roofing

Guttering

Barge Capping

Helpful Tips