Do you have a question about the Stratco FRONTIER and is the answer not in the manual?
Place stakes at carport post locations, tie string lines for alignment, and dig holes for posts.
Check concrete slab dimensions, mark post positions, and ensure alignment for on-concrete installations.
Pre-drill holes in C-Section beams and SHS posts for perimeter beams, and in intermediate beams/purlins.
Stand posts in footing locations and brace them securely with clamps and struts.
Bolt perimeter beams to posts using M12 bolts and washers, ensuring they are on the inside/outside face of posts.
Attach angle brackets to intermediate beams and purlins, then drill and bolt them to adjoining beams.
Concrete the footings and allow them to cure, finishing raised towards the column for water runoff.
Drill holes in the footing plate, then fix plates to the concrete slab using screwbolts.