6.3 Refrigerant circuit connection (A and AS units)
CyberRow A and AS units must be connected to a remote condenser. This condenser is not supplied together with
the unit.
Establishing the refrigerant connection consists of the following steps:
1. Selecting and laying the pipes.
2. Closing the circuit and testing the tightness with the conditioner and condenser stop valves closed.
3. Opening the valves and creating a vacuum.
4. Filling with refrigerant.
To design the piping between the A/C unit and the condenser follow the instructions in chapter "2. Refrigerant piping"
of document "General-DX". This document is available in the e-Stulz area.
6.3.1 Selecting and laying the pipes