52
Step 36 Install rotating face (51C) over high speed shaft (A130).
Step 37 Install o-ring (936J) over high speed shaft (A130).
Step 38 Install sleeve (50A) over high speed shaft (A130).
Step 39 Install o-ring (936J) over high speed shaft (A130 ASSY).
Step 40 Install o-ring (936H), lower process seal (60A) into seal housing (30).
Step 41 Install o-rings (936D), (936E), onto cover (15).
Step 42 Install cover (15) onto seal housing (30).
Step 43 Install rotating face (51A) over high speed shaft (A130).
Step 44 Install impeller bolt (3) into high speed shaft (A130).
Step 45 Install impeller (2) over impeller bolt (3).
Step 46 Install impeller bolt (3).
Step 47 Tighten impeller bolt (3) to correct torque specification, see Table 8.1.
Step 48 Install initial fill pipe (951D), (947L), (924RF), into upper gearbox housing (101B).
Step 49 Install vent pipe (951C), (947D), (186) into upper gearbox housing (101B).
Step 50 Install pressure gauge (942F), (177), (193C), into upper gearbox housing (101B).
Step 51 Reinstall the assembly of the gearbox/process end into the compressor housing (1).
Step 52 Reconnect all lubrication line and electrical connections.