6
1 - Mounting kit (part # SQ-RMK5) is required
Diagram Step 3b
Apply Teflon on two of the caps (SK-FTG-F). See Fig 3a-1.
Thread the 2 caps into the panels as per Diagram Step 3b. Do not over tighten.
See Fig 3a-2
Put "O" rings (SK-FTG-I) on both combination adapters (SK-FTG-D). See Fig 3a-3
Thread both combination adapters into the panels as per Diagram Step 3b.
Do not over tighten. See Fig 3a-4
Install mounting kits as per instructions included with them. Panels must be installed with a slight
slope (minimum 1 inch per 10 feet) toward the inlet. This will allow the panel to drain properly.
Note: The inlet must always be at the lower end of the panel and the outlet at the higher end of the panel.
3. c) Installation: multiple systems on ground.
A Minimum of 1 inch fall per 10 feet
Combination Adapter
Cap
Cap
Inlet
Outlet
Combination Adapter