Inspection, Repair
245
Chapter 10
1
2
3
4
5
6
7
8
9
10
11
5. Inspection, Repair
Before inspection, be sure to turn OFF the original power supply. Some circuits are still applied
voltage even if the original power supply was turned OFF. Wait until these circuits are completely
out of voltage (4 minutes) and then start working.
Inspection point Action Inspection cycle
Attaching of each type of cover Attach all the covers.
At start of working
Setting condition of embroidery
thread
Set it correctly.
Check breakage and/or bent of
needle.
Replace the needle.
Lubricating condition of each
section
Lubricate.
Belt tension (main shaft, X/Y
drive system)
Consult the distributor. Once/3 months
Before repairing the machine, be sure to turn OFF the main power supply. Some circuits are still
applied voltage even if the main power supply was turned OFF. Wait until these circuits are
completely out of voltage (4 minutes) and then start working.
If the machine needs the repair, the repair must be done only by the service personnel assigned
and trained by Tajima or qualified technician. (Consult your distributor.) Do not change the
specification nor modify the parts of the machine without due consultation with Tajima. Such
modification may have the risk against the operational safety.
When restarting the machine after repairs, attach all removed covers etc. as they were.
For the repair, use Tajima genuine parts for replacement.
SQ12