INSTRUCTIONS FOR TECHNICAL PERSONNEL
25
6) LOADING AND UNLOADING OF THE MACHINE
For the transportation of the machine from the delivery point to the final
installation position, use a fork lift or adequate lifting equipment used by
authorised staff. Lift the machine by its frame, taking care that any
protruding parts are not damaged (discharges, wiring etc.).
7) MACHINE DISMANTLING
At the end of its normal lifetime, the machine has to be taken apart according
to the local regulations in force by separating the components as follows:
metal parts: hood, platforms, frames, filters
electrical parts: motors, remote control switches, microswitches, wiring
plastic parts: racks, connections
rubber parts: tubes, sleeves
ENERGY CONSUMPTION
Model Wash
tank
capacity
(l)
Rinse water
consumpt.
(l)
Tank
heater
(W)
Booster
heater (W)
Wash
pump
(W)
Total
electric
load (W)
Output in
racks per
hour with
55°C inlet
water
Output in
racks per
hour with
12°C inlet
water
C86