COMMISSIONING
INSTALLATION & SERVICING INSTRUCTIONS
31
FINISHING COMMISSIONING
6-720-611-730b (12.05)
FINISHING COMMISSIONING
1 Engage top panel (A) onto rear retainers (B)
and lower front of panel into position.
Secure with screws (C).
2
Swing control panel assembly (D) into the
boiler.
Secure with screw (E).
3
Locate bottom corners of the front panel (F)
into retainers (G).
Hook top edge of panel (F) onto the retaining
ledge (H).
Lower into position to secure.
HANDOVER:
Complete the Benchmark log book.
Set up the controls and show the user how to
operate all the controls shown in the User Guide.
Instruct the customer how to repressurise the
system.
If the appliance is unused and exposed to freezing
conditions, advise the customer of the
precautions necessary to prevent damage to
the boiler, system and building.
In the event of the appliance being inoperative,
isolate the boiler and drain the system and boiler.