A Guide for Upgrading
CENTUM V and CENTUM-XL
to CENTUM VP (for Vnet/IP)
TI 33K01B10-50E
TI 33K01B10-50E
©Copyright Mar. 2015 (YK)
1st Edition Mar. 2015 (YK)
Yokogawa Electric Corporation
2-9-32, Nakacho, Musashino-shi, Tokyo, 180-8750 Japan
Tel.: 81-422-52-5634 Fax.: 81-422-52-9802
Question and Answer IconNeed help?

Do you have a question about the YOKOGAWA Centum-XL and is the answer not in the manual?

YOKOGAWA Centum-XL Specifications

General IconGeneral
ManufacturerYOKOGAWA
TypeDistributed Control System (DCS)
Control MethodDigital Control
Input/Output ModulesAnalog Input/Output, Digital Input/Output
Programming LanguageFunction Block Diagram (FBD), Sequential Function Chart (SFC)
ApplicationsProcess automation, plant monitoring
RedundancyDual-redundant control processors, power supplies, and communication networks

Summary

Preface

Trademarks

Registered and unregistered trademarks of Yokogawa Electric Corporation and other companies.

Abbreviated Terms

List of abbreviations and acronyms for Yokogawa products mentioned in the document.

The Need for Upgrade

System Deterioration Due to Aging

Explains system deterioration using a bathtub curve and factors affecting failure rates.

Following to the Change

Discusses the necessity of adopting new technologies and computer advancements for plant efficiency.

Increasing System Maintenance Cost

Details the rising costs associated with system maintenance due to aging and parts discontinuation.

Style of Upgrade

Batch-upgrade to Vnet/IP, FIO

Describes the batch upgrade process from CENTUM-XL/V to CENTUM VP (Vnet/IP, FIO).

Scope of Upgrade

Applicable Existing System

Lists CENTUM V and CENTUM-XL hardware and package software applicable for upgrade.

Procedure and Details of Upgrade

Upgrade Procedure

Outlines the step-by-step process for upgrading systems, including estimation and execution.

Details of Pre-assessment

Explains the purpose and flow of the pre-assessment process for ensuring system reliability.

Remedial Treatment

Details the proposed remedial treatments for equipment to ensure long-term stable operation.

Hardware Modification and Addition

Covers necessary hardware modifications and additions for the upgrade process.

Application Software Conversion

Describes the process and methods for converting application software during the upgrade.

On-site System Operations Check

Covers final on-site checks, tuning parameter adjustments, and operation timing.

Maintenance After Upgrade

Discusses maintenance services and recommendations for upgraded systems.

System Functions After Upgrade

System Overview

Describes enhancements of overall control functions in upgraded FCS.

Upgrade Specifications

Details standards and specifications for upgrade work, including node numbering and tag names.

Application Capacity of Upgraded FCS

Compares application capacities of CENTUM V, XL, and upgraded CENTUM VP systems.