36 Installation checklist
4. Internal cabling to integrated transformer (power, auxiliary, control and
heater cables) made according to the instructions in this manual
(
Electrical installation)
5. Cable entry made according to the instructions in this manual ( Electrical
installation)
6. All control cable screens and conductors are connected according to the
instructions in this manual (
Electrical installation), appropriately labeled,
and the customer-side connections are completed
7. Heating cable (if supplied) installed according to the instructions in this
manual (
Electrical installation)
8. Ground cable of drive securely connected at both ends
9. Input and motor cables not connected at both ends (cables must be
meggered before connection, drive optional - recommended in case of
long storage time, humid environment or visible transportation
damages)