Table 236. Scheme communication functions
Function Function
identification
Ordering no Position Available
qty
Selected
qty
Notes and
rules
Scheme communication logic with delta based blocking
scheme signal transmit
ZCPSCH 1MRK005920-AA 1 0-2
1)
Phase segregated scheme communication logic for distance
protection
ZC1PPSCH 1MRK005920-BA 2 0-2
Current reversal and weak-end infeed logic for distance
protection
ZCRWPSCH 1MRK005920-CA 3 0-2
2)
Current reversal and weak-end infeed logic for phase
segregated communication
ZC1WPSCH 1MRK005920-DA 4 0-2
Local acceleration logic ZCLCPSCH 1MRK005920-EA 5 0-1
Scheme communication logic for residual overcurrent
protection
ECPSCH 1MRK005920-FA 6 0-1
Current reversal and weak-end infeed logic for residual
overcurrent protection
ECRWPSCH 1MRK005920-GA 7 0-1
Direct transfer trip DTT 1MRK005921-AY 8 0-1
1) Only one of ZCPSCH/ZC1PPSCH can be selected.
2) Only one of ZCRWPSCH/ZC1WPSCH can be selected.
Table 237. Logic
Position 1 2 3
L 00
Table 238. Logic functions
Function Function
identification
Ordering no Position Available
qty
Selected
qty
Notes and rules
Configurable logic blocks Q/T 1MRK005922-MX 1 0-1
Extension logic package 1MRK005922-DB 2 0-1
Table 239. Monitoring
Position 1 2 3 4
M 1 0
Table 240. Monitoring functions
Function Function
identification
Ordering no Position Available
qty
Selected
qty
Notes and rules
Circuit breaker condition monitoring SSCBR 1MRK005924-HA 1 00-06
Fault locator LMBRFLO 1MRK005925-XE 2 1
Through fault monitoring PTRSTHR 1MRK005924-TA 4 0–2
Current harmonic monitoring, 3 phase CHMMHAI 1MRK005924-QA 5 0–3
Voltage harmonic monitoring, 3 phase VHMMHAI 1MRK005924-SA 6 0–3
Table 241. Station communication
Position 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
P 0 0 0 0 0 0 0 0 0 0 0 0 0
Table 242. Station communication functions
Function Function
identification
Ordering no Position Available
qty
Selected
qty
Notes and rules
IEC 61850-9-2 Process bus communication, 8 merging units 1MRK005933-HC 1 0-1
IEC 62439-3 Parallel redundancy protocol PRP 1MRK005932-FA 2 0-1
1)
IEC 62439-3 High-availability seamless redundancy HSR 1MRK005932-NA 3 0-1
Synchrophasor report, 8 phasors 1MRK005933-DA 15 0-1
2)
1) PRP and HSR require two SFPs placed in pairs.
2) This functionality requires accurate time synchronization, therefore either ‘Precision Time Protocol (PTP) Time synch or GTM or IRIG-B will be required.
Line differential protection RED670
1MRK 505 379-BEN N
164 Hitachi Power Grids