20
2.7.g. 28-Day Timer
Each 28-Day timer has Program 1-4 for programming the various feed times. While the programming steps
for four programs are the same, each can have its own independent settings.
WEEKS - The week(s) that the timer is to feed.
DAYS - The day(s) that the timer is to feed.
START - The time of day for the timer to start.
RUN - How long the timer is to run.
PREBLEED - How long the controller is to bleed down
before feeding in chemical. Note: The prebleed starts
at the START time programmed above.
MIN COND - The minimum conductivity that the unit
will prebleed down to.
FEED LOCK - Which other system timer to lockout
BLEED LOCK
FLOW LOCK
NOTE: ORP lock is only for systems with the ORP function. If interlocked, the ORP setpoint will switch to
to a relay activated by the ORP setpoint/control function.
2.8. Alarms
ALARMS - Shows any current alarms. Accessible from
the Setup/Run screen.