010-619-J0 Rev B Page 31
Slide the connection point assembly back into the distribution module and secure with the thumbscrew
lock. Note the cable(s) and the connection points positioned for proper access.
Figure 22: Breaker Return Connections (Four Load Breaker Configuration shown)
Breaker Hot Connections
Connect to the four load breaker hot (–) termination pairs using 1/4" on 5/8" center lugs. Connection
method is similar for breaker distributions in a 2 load/2 battery CB configuration. Refer to the connection
drawing.
Figure 23: Front View of Distribution Module (Four Load Breaker Configuration shown)
GMT Fuse Distribution
The ten (10) GMT-style fuses and the associated terminal blocks are accessible from the front panel of
the distribution module (Refer to the connection drawing).