AMCOT ST SERIES FIBERGLASS COOLING TOWER
- 10 -
STARTUP INSPECTION
Once your cooling tower has been properly installed by licensed professionals, proper startup of the unit
should occur. Below is a checklist of items to verify prior to performing initial startup of your unit and
after seasonal shutdowns.
GENERAL PROCEDURES
REMEMBER TO ALWAYS SHUT DOWN AND PERFORM LOCKOUT/TAG-OUT PROCEDURES
PRIOR TO SERVICING OR ACCESSING YOUR EQUIPMENT!
Unit should be installed level and on proper footings or foundations made from concrete or
steel.
o Uneven foundations can impact equipment service life and void your warranty.
Units should be secured and fastened according to the unit’s foundation drawing.
o Failure to properly secure the unit can cause equipment damage and void your
warranty.
Circulating water pump suction connection must be below the outlet connection to the cooling
tower.
o Failure to properly install your pump will cause damage to not only the pump’s
components but also can impact your overall system design.
All piping should be properly supported. The cooling tower is not designed to be or act as a pipe
support.
o Failure to properly secure piping can cause physical damage to the cooling tower and
void your warranty.
Inlet and Outlet connections should incorporate flex connections at the point of connection to
help isolate vibration from the tower or the pump.
All piping connections should have operable valves for proper water balancing and tower
isolation and servicing.
Ensure your disconnect switch is properly installed and working.
Any safety interlocks should be tested.
When operating ST Series towers on inverter drives or Variable Frequency Drives, make sure the
minimum speed requirements have been programmed.
o Standard Fan Motors on the ST Series can be operated on variable frequency drives with
an operating range of 20-60 hertz.
Verify all valves, sensors, gauges, or other accessories are working properly.
Amcot recommends a local water treatment specialist provide you with a water treatment
program that is suitable for your local conditions.
o Failure to implement and maintain a water treatment plan may void your tower
warranty as this is the responsibility of the owner to maintain such plans.
Make sure all electrical connections are secure.
Check inside your tower and remove any debris.
Check under or around your tower for any signs of water leaks.