Quartz bath with overflow filler installation instructions Page 7
Installation instructions
70mm
90mm
445mm
270mm
350mm
265mm
To ensure safe operation and installation of this product, the
processor MUST be installed in one of the orientations shown.
1
Isolation valves are supplied with the
Digital processor and must be fitted on
both inlets and the blended water outlet.
All pipe work should be run in 15mm
pipe. All pipe work should be supported.
For externally pumped gravity fed
installations, 22mm pipe work should be
run as close to the processor as possible before reducing down
to 15mm.
2
The inlet supply centres are 48mm. The inlet supply centres
deviate from EN1111 and EN1287, but are deemed to be a
special case. Please note arrow on isolation valve to indicate
direction of flow.
Compression fittings should not be used on the inlet and outlet
spigots and may affect the warranty if fitted.
!
This product must be installed by a competent person in accordance
with the relevant Water Supply Regulations.
Fit the Digital processor and main controller following the main unit
installation instructions provided.
Prior to connecting the blended supply connections to the shower/bath
fittings, follow the procedure below to install the Digital diverter valve.
!
!
!