| 7 |
1. It is recommended that the meter will NOT be installed in the middle of the system,
so the meter will not suer from the load of all the installed xtures.
13.0 Polymeric Octave Installation - General Instructions
Please follow the general instructions for water meters (Check Valve, upstream & down stream and system ushing
on new installations).
Existing and new installations:
2. It is recommended that at least one side of meter will be connected to a PVC (or plastic) pipe.
1 mm max
Rubber
gasket
4. When using standard tail piece, please use rubber gaskets only (not berglass)! After adding the gaskets the gap
between the end connection and the meter should not exceed 1mm.
Please unscrew the end connection in order to keep the recommended distance.
• Please do not use force in order to close the gap.
• Please don’t do any welding while the meter is connected to the pipe.
3. Please make sure that the end connections are parallel and inline to each other.