Commissioning
With first commissioning basic settings and tests are carried out. Please ensure that all information for this is
available. With input of the plant values all important parameters are pre-set. However, we recommend that,
following commissioning, the parameters are again checked under Settings, as false values can, inter alia, lead
to an increased power consumption.
In the Service Mode you have the possibility later of undertaking modifications.
Language selection
Enter language you need.
Password input
Please enter the six-figure code number.
Date and time
Enter the date and time.
Important for the correct entries in the logbook
Selection of the plant type
Select between BASIC, CLASSIC or AQUAPRIMO.
Number of inhabitants
Select the connected PT.
The settings belonging to the number of inhabitants are carried out automatically.
Serial number
Enter the serial number, which is located on the frame of the AQUAmax
®
(not the serial
number of the control unit), here. Please ensure that the serial number is entered right-
aligned, in order that leading zeros result.
New plant?
With yes the sludge return feed is suppressed for half a year (run-in phase).
Test run
In test run operation the current float level and the current power input are indicated.
Pressing OK carries out the test run.