AUX-DC inverter ARV outdoor unit individual series technical manual
90
1. Preparation on installation
1.1 Installation procedure
1.2 Preparation and Tools before Installation
Please buy the following parts from the market before installation
Hanging bolt4 per unit
PVC drainage pipe
Some cable ties
Connecting copper pipe
Branch pipe (choose according to actual installation situation)
Thermal insulation materials for copper pipe and drainage pipe.
PEF foaming materials with thickness above 8mm
Power wire and communication wire.
It’s required to wire according to requirement for line diameter in wiring diagram
Note:
It’s necessary to use dedicated tools of R410A for some tools during installation.
The selected position hanging indoor unit should be able to support the weight of unit without noise
and additional vibration. It’s necessary to reinforce before installation if reinforcement is required;
The space of selected ceiling should be enough for holding indoor unit;

Table of Contents

Other manuals for AUX ARV Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the AUX ARV Series and is the answer not in the manual?

AUX ARV Series Specifications

General IconGeneral
BrandAUX
ModelARV Series
CategoryAir Conditioner
LanguageEnglish

Related product manuals