10 Scheduled maintenance
SCHEDULED MAINTENANCE VALVE GASKETS ACTUATOR GASKETS
Preventive Replace after 12 months Replace after 24 months
In the event of leaks Replace at the end of the day Replace in the event of leaks
Periodical
Check correct operation and
that there are no leaks
Check correct operation and
that there are no leaks
Record the actions carried out Record the actions carried out