Operation
Wire ropes
• Check wire ropes for integrity and corrosion before start-up. Treat wire ropes in accordance
with the additional documentation "Maintenance and care of wire ropes".
Process fitting
Kelly bar
• Check that the fully extended Kelly bar is in proper working order before start-up. If necessary,
restore the Kelly bar to its proper condition or replace it with a new one.
Rotary drive
• Service the rotary drive in accordance with the maintenance table before start-up.
Daily start-up
Visual check before daily start-up
Risk of causing damage to equipment!
Any unresolved deficiencies can cause damage to the equipment.
Δ
Visually check the equipment before each start-up.
Δ
Have the defect repaired by skilled personnel immediately.
• Check the entire equipment and accessories for completeness.
• Make sure that the screw connections and plug connections on the machine and accessories
are secure and complete.
• Check all components, particularly load-bearing steel components and rope, for integrity and
wear.
• Check all electrical, hydraulic and pneumatic components for integrity and correct connection.
• Be sure to check for fluid build-ups or leaks.
• Ensure all operating fluids are at required levels.
• Compare the hours on the operating hours meter with the specified maintenance intervals and
perform any pending maintenance tasks.
• Check that lighting equipment is in proper working order.
• Check that signaling devices are in proper working order.
• Check that camera equipment is in proper working order.
✓ Visual inspection has been properly carried out.