Operation
Wire ropes
Check wire ropes for integrity and corrosion before start-up. Treat wire ropes in accordance
with the additional documentation "Maintenance and care of wire ropes".
Process fitting
Kelly bar
Check that the fully extended Kelly bar is in proper working order before start-up. If necessary,
restore the Kelly bar to its proper condition or replace it with a new one.
Rotary drive
Service the rotary drive in accordance with the maintenance table before start-up.
Daily start-up
Visual check before daily start-up
Risk of causing damage to equipment!
Any unresolved deficiencies can cause damage to the equipment.
Δ
Visually check the equipment before each start-up.
Δ
Have the defect repaired by skilled personnel immediately.
Check the entire equipment and accessories for completeness.
Make sure that the screw connections and plug connections on the machine and accessories
are secure and complete.
Check all components, particularly load-bearing steel components and rope, for integrity and
wear.
Check all electrical, hydraulic and pneumatic components for integrity and correct connection.
Be sure to check for fluid build-ups or leaks.
Ensure all operating fluids are at required levels.
Compare the hours on the operating hours meter with the specified maintenance intervals and
perform any pending maintenance tasks.
Check that lighting equipment is in proper working order.
Check that signaling devices are in proper working order.
Check that camera equipment is in proper working order.
Visual inspection has been properly carried out.