7
IMPORTANT INSTRUCTIONS
These instructions must be followed to ensure proper installation and operation
of your lift. Failure to comply with these instructions can result in serious
bodily harm and void product warranty. Manufacturer will assume no liability for
loss or damage of any kind, expressed or implied, resulting from
improper installation or use of this product.
PLEASE READ ENTIRE MANUAL PRIOR TO INSTALLATION
SECTION 1
(SELECTING SITE)
Before installing your new lift, check the following.
1. LIFT LOCATION: Always use architectural plans
when available. Check the layout dimension against the
oor plan requirements, making sure that adequate space
is available.
2. OVERHEAD OBSTRUCTIONS: The area where the
lift will be located should be free of overhead obstructions
such as heaters, building supports, electrical lines, etc.
3. DEFECTIVE FLOOR: Visually inspect the site where
the lift is to be installed and check for cracked or defective
concrete.
4. Lift is designed for INDOOR INSTALLATION ONLY.
Outdoor installation is prohibited. Always follow warnings
illustrated on equipment labels.
SECTION 2
(FLOOR REQUIREMENTS)
This lift must be installed on a solid level concrete
floor with no more than 3-degrees of slope. Failure
to do so could cause personal injury or death.
A level oor is suggested for proper use, installation
and level lifting. If a oor is of questionable slope, con-
sider a survey of the site and/or the possibility of pouring
a new level concrete slab.
t DO NOT install or use this lift on any asphalt surface
or any surface other than concrete.
t DO NOT install or use this lift on expansion seams
or on cracked or defective concrete.
t DO NOT install or use this lift on a second / elevated
oor without rst consulting building architect.
t DO NOT install or use this lift in extremely damp
environments.
t DO NOT install this lift outside. It is only approved for
indoor installations.
t Refer to ANSI/ALI ALIS Standard (R2015) Safety
Requirements for Installation and Service for more
information about safely installing your Lift.
ALL MODELS MUST BE INSTALLED ON CONCRETE
ONLY CONFORMING TO THE MINIMUM
REQUIREMENTS SHOWN ABOVE. NEW CONCRETE
MUST BE ADEQUATELY CURED BY AT LEAST
28 DAYS MINIMUM.
OUR LIFTS ARE SHIPPED WITHOUT OIL.
ADD OIL TO POWER UNIT TANK BEFORE USE.
LIFT MODEL CONCRETE REQUIREMENTS
PCL-18B 5” Min Thickness