blueberry PLUS R2 Installation Manual 3.0 38
7. COMMISSIONING
7.1. Installation Validation
Before starting up blueberry charging station:
Must be done the following inspections:
#
TOPIC:
OK / NOK
1.
Site complying with clearance conditions and safety
requirements
2.
Absence of physical and structural damage
3.
Charger ground fixation and leveling complies with manual
requirements
4.
Locking system is closing adequately
5.
Upstream protection rating in Low voltage distribution board is
according with the manual (refer chapter 5.3)
Must be done the following measurements:
#
TOPIC:
6.
Confirm AC voltage between phases and phases and ground. The voltage must be
according to the local grid and within blueberry charger range (refer chapter 3.1)
7.
Confirm DC Power Interconnections (refer chapter 5.4)
8.
Confirm communications interconnections (refer chapter 5.4)