Page 3
Installation
Checklist – prior to installation of espresso machine
1. Required bench space:
2. Remove the top lid and water inlet hose (braided), which is located at the back of the
machine
3. Ensure holes are drilled through a bench or wall as required (minimum 50mm)
4. The power point must be within 1 meter of the machine
1 Group – 10amps Grinders – 10amps
2 Groups – 15amps
3 Groups – 20amps
5. Cold water 1/2 inch male stop cock fitted within 1 meter of machine
6. Drainage – via bucket or into plumbing (gravity fed)
7. Water connected / Power connected
Recommended:
350 KPA Pressure Limiting valve be fitted in line by your plumber with a half inch male fitting.
Your warranty requires you to fit the appropriate water filter to suit your local conditions. Boema has a
complete range of water filters to suit all conditions. The supplied filter may not be suitable in regional
areas.
Installations by Technicians include
- Connection to water and power services, which are already provided
- Commissioning of the machine
- Demonstration of the use of the machine
- Operator maintenance demonstration
Hole 50mm
300mm
300mm front left – Operating Side