Bearing time / months
Measures for commissioning
> 1 > 12 > 60
■ Exchange bearings
■ Exchange encoders
Tab. 5-1: Measures before commissioning motors that have been stored over
a prolonged period of time
Cables and Connectors
Bearing time / months
Measures for commissioning
> 1 > 12 > 60
■ ■ ■ Visual inspection of all parts to be damage-free
■ ■
Check the electric contacts to verify that they are free from
corrosion
■
Visually inspect the cable jacket. Do not use the cable if
you detect any abnormalities (squeezed or kinked spots,
color deviations, ...).
Tab. 5-2: Measure before commissioning cables and connectors that have
been stored over a prolonged period of time
MSK Synchronous Servomotors 17/57
Transport and storage
R911325169_Edition 03 Bosch Rexroth AG