CHECKLIST—INSTALLATION
LOAD CALCULATION
_________________ Heating Load (Btuh)
_________________ Cooling Load (Btuh)
_________________ Furnace Model Selection
AIR FOR COMBUSTION AND VENTILATION
_________________ Unconfined Space
_________________ Confined Space
VENTING
_________________ NFGC (United States)
_________________ NSCNGPIC (Canada)
_________________ Local Codes
_________________ 1/4-in. Upward Slope
_________________ Joints Secure
_________________ See Vent Table Instructions
CHECKLIST—START-UP
_________________
Gas Input Rate
(Set Within 2 percent of Rating Plate)
_________________ Temperature Rise Adjusted
_________________ Thermostat Anticipator Setting or
_________________ Thermostat Cycle Rate (3 cycles per Hr)
CHECK SAFETY CONTROLS OPERATION
_________________ Primary Limit
_________________ Pressure Switches
_________________ Draft Safeguard Switch
_________________ Auxiliary Limit Switch(es)
Thermostat
_________________ Manufacturer
_________________ Model number
—21—