START-UP CHECKLIST FOR 09FC WATERSIDE ECONOMIZER
(Remove and use for Job File)
A. PROJECT INFORMATION
Job name _____________________________________
Address _____________________________________
City ______________________State ____Zip_________
Equipment tag/mark for____________________________
Installing contractor_______________________________
Sales office _____________________________________
Start-up performed by_____________________________
Unit
Model ____________________________________ Serial________________________________________
B. PRELIMINARY EQUIPMENT CHECK (This section to be completed by installing contractor)
1. Is there any physical damage? Yes No
Will this prevent start-up? Yes No
Description:
2. Power supply agrees with the unit nameplate. Yes No
3. Correct control voltage ________vac. Yes No
4. Electrical power wiring is installed properly. Yes No
5. Unit is properly grounded. Yes No
6. Electrical circuit protection has been sized and installed properly. Yes No
7. All terminals are tight. Yes No
8. All plug assemblies are tight. Yes No
9. All cables and thermistors have been inspected for cross wires. Yes No
10. All thermistors are installed and fully inserted into wells. Yes No
Chilled Water System Check
1. All water valves are open. Yes No
2. All piping is connected properly. Yes No
3. All air has been purged from the system. Yes No
4. Units installed in open loop: inlet piping to evaporator includes a 20 mesh strainer
within 10 ft of unit. Yes No
5. Water loop volume greater than 3 gal/ton (40 L/kW) for air conditioning
or 6 gal/ton (80 L/kW) for process cooling and low ambient operation. Yes No
6. Proper loop freeze protection provided to ____ F (C).
Antifreeze type__________________ Concentration _____%. Yes No
NOTE: To avoid injury to personnel and damage to equipment or
property when completing the procedures listed in this start-up
checklist, use good judgment, follow safe practices, and adhere
to the safety considerations/information as outlined in
preceding sections of this Installation, Start-Up and
Maintenance document.