EasyManua.ls Logo

Carrier 58UVB series User Manual

Carrier 58UVB series
50 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
Page #1 background imageLoading...
Page #1 background image
58UVB
D i r e c t --- Ve n t U p f l o w
Variable---C apacity Condensing Gas Furnace
For Sizes 060---120, Series 100
Installation, Start---Up, and
Operating Instructions
NOTE: Read the entire instruction manual before starting the
installation.
TABLE OF CONTENTS
PAGE
SAFETY CONSIDERATIONS 2........................
DIMENSIONAL DRAWING 3..........................
Clearances to Combustibles 4........................
CODES AND STANDARDS 5..........................
ELECTROSTATIC DISCHARGE (ESD) PRECAUTIONS 6..
INTRODUCTION 6..................................
APPLICATIONS 6...................................
General 6........................................
Applications 6.....................................
LOCATION 8.......................................
General 8........................................
Low--Heat Only Installation 10........................
Location Relative to Cooling Equipment 10..............
Hazardous Locations 10.............................
INSTALLATION 10..................................
Leveling Legs (If Desired) 10.........................
Air Ducts 11.......................................
Filter Arrangement 11...............................
Bottom Closure Panel 12.............................
Gas Piping 12.....................................
Electrical Connections 14............................
Removal of Existing Furnaces from Common Vent Systems 17
Combustion--air and Vent Pipe Systems 18...............
Condensate Drain 32................................
START--UP, ADJUSTMENTS, AND SAFETY CHECK 33...
General 33........................................
UPFLOW
AIRFLOW
A06340
Fig. 1 --- Furnace Orientation
ama
CERTIFIED
As an ENERGY STAR® Partner ,
Carrier Corporation has deter-
mined that this product meets
the ENERGY STAR® guidelines
for energy efficiency.
REGISTERED
ISO 9001:2000
Select Setup Switch Positions 33.......................
Prime Condensate Trap with Water 34...................
Purge Gas Lines 35.................................
Sequence of Operation 35............................
Adjustments 43....................................
Check Safety Controls 48............................
CHECKLIST 49.....................................
Question and Answer IconNeed help?

Do you have a question about the Carrier 58UVB series and is the answer not in the manual?

Carrier 58UVB series Specifications

General IconGeneral
BrandCarrier
Model58UVB series
CategoryFurnace
LanguageEnglish

Summary

Safety Considerations

General Safety Precautions and Hazards

Details essential safety measures, PPE, and critical hazards like fire, shock, and CO poisoning.

Installation Location Safety

Specifies requirements for furnace placement, including clearances and approved locations.

Installation

Leveling Legs and Floor Mounting

Details the process for installing leveling legs if desired for furnace support.

Ductwork Connections and Requirements

Covers design and sizing of duct systems, supply and return air connections.

Gas Piping and Connections

Outlines national and local codes for gas piping installation, including pressure testing.

Electrical Connections and Wiring

Details electrical connection requirements, voltage compatibility, and wiring diagrams.

Combustion Air and Vent Pipe Systems

Explains direct vent and ventilated combustion air system options and their requirements.

Vent and Combustion Air Pipe Sizing and Installation

Provides guidelines for sizing, installing, and insulating combustion air and vent pipes.

Vent Termination Clearances

Specifies required clearances for vent terminals above grade, windows, soffits, and other structures.

Condensate Drain System

Details the installation and protection of the condensate drain system, including trap priming.

Start-Up, Adjustments, and Safety Check

Initial Start-Up and General Checks

Outlines initial checks for power, grounding, thermostat wiring, and blower door installation.

Setup Switch Configuration

Explains how to configure setup switches for A/C, CF, and other operational modes.

Priming the Condensate Trap

Describes the process of priming the condensate trap to ensure proper draining.

Gas Input Rate and Manifold Pressure Adjustment

Details how to set gas input rate and manifold pressure according to altitude and gas properties.

Temperature Rise Measurement

Explains how to measure and ensure the air temperature rise is within specified limits.

Safety Control Checks

Covers verification of the primary limit control and pressure switches for safe operation.

Installation Checklist

Provides a comprehensive checklist to ensure all installation steps are completed correctly.

Related product manuals