4 - LOCATING BOILER
FIGURE 4-1 Clearance to Combustible Materials
4.1 Boiler Location Considerations
Ambient room temperature always above 32°F (0°C) to
prevent freezing of liquid condensate.
Approved for installation in closets.
Protect gas ignition system components from water
(dripping, spraying, rain, etc.) during operation and
service (circulator replacement, condensate trap, control
replacement, etc.).
• Wall mounting.
Wall must be plumb and capable of supporting boiler
weight plus 60 lbs (28 kg). See Table 1, page 2.
Wall mounting. See section 4.2.
Access to outdoors to meet minimum and maximum
pipe lengths for combustion air and vent piping. See
section 6.
Disposal of condensate. See section 6.
Drainage of water (or water - antifreeze solution) during
boiler service or from safety relief valve discharge. See
section 5.
Access to system water piping, gas supply, and electrical
service. See sections 5, 7 and 8.
Clearances to combustible materials and service
clearances. See Table 2 and gure 4-1.
Multiple Boilers can be wall mounted, placed side by
side, or back to back.
TABLE 2: BOILER CLEARANCES
Dimension
Combustible
Materials
(1)
Service
(1)(2)
Model
050/075/100/
150/200
050/075/100/
150/200
Top (A)
0" (0 cm) 14" (36 cm)
Left Side (B)
0" (0 cm) 0" (0 cm)
Right Side (C)
0" (0 cm) 0" (0 cm)
Front (D)
0" (0 cm) 6" (16 cm)
Back (E)
0" (0 cm) 0" (0 cm)
Bottom (F)
0" (0 cm) 12" (32 cm)
Combustion Air/Vent
piping
0" (0 cm)
6" (16 cm)
Hot Water Piping
½" (1.3 cm) 6" (16 cm)
(1)
Required distances measured from boiler.
(2)
Service, proper operation clearance recommendation.
A
E
E
D
A
C
B
A
FLOOR
FLOOR
A
D
F
F
F
F