62-10327 18
OPERATIONAL INSPECTION
Refer to Warnings and Notes on page 2 before proceeding.
1. Remove the Lock Out/Tag Out device and plug unit in to power
supply. Check that voltage is good on all 3 phases.
2. Install the manifold gauge set using good system hygiene practices.
For PrimeLINE units, operating pressures can be viewed by going to
code 12 (Suction Pressure) and code 14 (Discharge Pressure).
3. Turn unit power on and change the set point to 32ºF (0ºC). Check
Container ID on start up to ensure correct set up and also verify the
date and time is set to GMT. Check that the correct software and
configuration are loaded in the MicroLink controller on start up or
check at codes 18 and 20. Note: It is recommended to have
always the latest operational software loaded in the controller.
4. Check the condenser and both evaporator fans for proper rotation
(Refer to Figure 22).
Figure 22 Evaporator and Condenser Fans Proper Rotation