S The Y2 In call will be satisfied with the damper 100%
open and fan on high speed and the call will turn off
OR
S If the call for additional cooling in the space has not
been satisfied then the first stage of mechanical cooling
will be enabled through Y1 Out or Y2 Out.
CHECKOUT
Inspect all wiring connections at the Economizer module’s
terminals, and verify compliance with the installation
wiring diagrams.
For checkout, review the Status of each configured
parameter and perform the Checkout tests.
NOTE: See “Interface Overview” on page 11. for
information about menu navigation and use of the keypad.
ELECTRICAL SHOCK HAZARD
Failure to follow this warning could cause personal
injury, death or property damage.
Before performing service or maintenance operations
on unit, always turn off main power switch to unit and
install lock(s) and lockout tag(s). Unit may have more
than one power switch. Ensure electrical service to
rooftop unit agrees with voltage an amperage listed on
the unit rating plate.
If any wiring changes are required, first be sure to
remove power from the Economizer module before
starting work. Pay particular attention to verifying the
power connection (24 Vac).
!
WARNING
Power Up
After the W7220 module is mounted and wired, apply
power.
Initial Menu Display
On initial start up, Honeywell displays on the first line
and Economizer W7220 on the second line. After a brief
pause, the revision of the software appears on the first line
and the second line will be blank.
Power Loss (Outage or Brownout)
All setpoints and advanced settings are restored
a
after any
power loss or interruption.
a
All settings are stored in non ---volatile flash memory.
Status
Use the Status menu (see Table 5) to check the parameter
values for the various devices and sensors configured.
NOTE: See “Interface Overview” on page 11. for
information about menu navigation and use of the keypad.
Checkout Tests
Use the Checkout menu (on page 16) to test the damper
operation and any configured outputs. Only items that are
configured are shown in the Checkout menu.
NOTE: See “Interface Overview” on page 11. for
information about menu navigation and use of the keypad.
To perform a Checkout test:
1. Scroll to the desired test in the Checkout menu using
the the
and buttons.
2. Press the
button to select the item.
3. RUN? appears.
4. Press the
button to start the test.
5. The unit pauses and then displays IN PROGRESS.
6. When the test is complete, DONE appears.
7. When all desired parameters have been tested, press
the
(Menu up) button to end the test.
The Checkout tests can all be performed at the time of
installation or at any time during the operation of the
system as a test that the system is operable.
EQUIPMENT DAMAGE HAZARD
Failure to follow this caution may result in equipment
damage.
Be sure to allow enough time for compressor startup
and shutdown between checkout tests so that you do
not short--cycle the compressors.
CAUTION
!