Manufacturer reserves the right to discontinue, or change at any time, specifications or designs without notice and without incurring obligations.
Catalog No. 04-53480209-01 Printed in U.S.A. Form 48FC-4-7-01SI Pg CL-1  1018 8-18 Replaces: NEW
START-UP CHECKLIST FOR 48FC04-07 SINGLE PACKAGE ROOFTOP
GAS HEATING/ELECTRIC COOLING UNIT 
(REMOVE AND USE FOR JOB FILE) 
I. PRELIMINARY INFORMATION
MODEL NO ____________________________________________
JOB NAME_____________________________________________
SERIAL NO ____________________________________________
ADDRESS _____________________________________________
START-UP DATE________________________________________
TECHNICIAN NAME _____________________________________
ADDITIONAL ACCESSORIES
_____________________________________________________________________________________________________
II. PRE-START-UP
Verify that all packaging materials have been removed from unit  (Y/N) _____
Verify installation of outdoor air hood  (Y/N) _____
Verify installation of flue exhaust and inlet hood  (Y/N) _____
Verify that condensate connection is installed per instructions    (Y/N) _____
Verify that all electrical connections and terminals are tight  (Y/N) _____
Verify gas pressure to unit gas valve is within specified range  (Y/N) _____
Check gas piping for leaks  (Y/N) _____
Check that indoor-air filters are clean and in place  (Y/N) _____
Check that outdoor air inlet screens are in place (Y/N) _____
Verify that unit is level  (Y/N) _____
Verify that fan assembly is free of obstructions and rotor spins freely  (Y/N) _____
Verify that scroll compressors are rotating in the correct direction  (Y/N) _____
Verify installation of thermostat  (Y/N) _____
Verify that crankcase heaters have been energized for at least 24 hours  (Y/N) _____
III. START-UP
ELECTRICAL
Supply Voltage  L1-L2_____________ L2-L3_____________ L3-L1_____________
Compressor Amps 1 L1   _____________ L2   _____________ L3   _____________
Compressor Amps 2 L1   _____________ L2   _____________ L3   _____________
Supply Fan Amps L1   _____________ L2   _____________ L3   _____________
TEMPERATURES
Outdoor-air Temperature  _____________ °F DB (Dry Bulb)
Return-air Temperature  _____________ °F DB  _____________ °F WB (Wet Bulb) 
Cooling Supply Air Temperature  _____________ °F
Gas Heat Supply Air  _____________ °F
NOTE:  To avoid injury to personnel and damage to equipment or
property when completing the procedures listed in this start-up
checklist, use good judgment, follow safe practices, and adhere
to the safety considerations/information as outlined in preced-
ing sections of this Installation Instruction document.