WHEN MIXING END:
a) Open pouring valve ( REF. 8 ) and check the correct flask filling.
b) We suggest to switch on the VIB button to have a slight vibration during the mixture
pouring for a better flask filling. To adjust intensity push + or– where is VIB button on
the control panel.
c) After the first flask has been filled, close valve ( REF. 8 ) and turn the flask plate until
next flask will reach correct positioning. Open again the valve for the flask filling.
d) If the vacuum value on the vacuum meter gauge has not been lowered,
IT IS NOT NECESSARY TO START THE VACUUM PUMP AGAIN.
switch on the pump just if the vacuum gauge has gone below – 60
WHEN FLASK HAS BEEN TOTALLY FILLED:
a) Start the vibration process ( max 3 minutes ) by pushing VIB on the control panel.
b) Adjust the vibration intensity according to flask size and quantity.
c) Switch off the vibration
d) Release vacuum by opening vacuum tap ( REF. 5 ) until vacuum gauge will reach zero.
e)
FINAL OPERATIONS:
f) Leave flasks into the unit for the mixture hardening.
g) Remove the mixing chamber and the mixing blade and care to wash and rinse all their
parts, specially the bottom part of the mixing container where it is located the pouring
valve and its spring.
h) Dry the container and the blade before using them for a new operation
i) Clean the internal part of the top cover and cap especially where the blade shaft
connection.
j) take the flask plate completely off the machine.
k) This particular process phase is very delicate: be careful in the flask moving because
this is the most delicate moment for the accurate mould reproduction and copy during
the mixture hardening .That’s why we deliver with the unit a spare extra flask plate.
l) Load again water level into the dosing tank
m) The unit is now ready for another investment preparation process.