PROCESS START:
BEFORE PROCEEDING THR MIXING OPERATION PLEASE VERIFY:
a) PRESETTED MIXING TIME ( SECONDS ON EXTREME RIGHT SIDE OF THE LED DISPLAY )
To set the value that will be kept always in memory until an eventual change: push + or – ( TIMER )
ATTENTION: ONCE TIME HAS BEEN SETTED, IT WILL WORKS AUTOMATICALLY AND WHEN
MIXER WILL START UNTIL THE MIXING END. AT THE END OF MIXING, THE VALUE WILL COME BACK
TO THE ORIGINAL SETTED TIME FOR THE NEXT OPERATION.
AT THE END OF THE MIXING TIME ONE BUZZER WILL SOUND TO INFORM THE OPERATOR THAT THE
MIXTURE IS NOW READY FOR THE POURING STEP.
DURING THE MIXING PROCESS, IF EVENTUALLY THE MACHINE WILL BE STOPPED, THE TIMER
WILL START AGAIN FROM THE INITIAL PRESETTED TOTAL TIME.
b) BLADE ROTATION DIRECTION : ( LEFT TOP PART ARROW ON LED DISPLAY )
WE SUGGEST TO START MIXING ALWAYS FROM LEFT TO RIGHT SIDE.
BY PUSHING INV. MOT BUTTON IT IS POSSIBLE TO CHANGE THE BLADE DIRECTION
( AN OPTION THAT OCCASIONALLY COULD BE USEFUL ).
BY PUSHING + OR - UNDER MIX BUTTON LOCATION, IT IS POSSIBLE TO ADJUST THE BLADE
SPEED ROTATION.
ONCE CHECKED THE ABOVE PARAMETERS, CHECK IF THE VACUUM TAP (REF. 5) IS CLOSED.
BY HOLDING WITH ONE HAND THE TAP CLOSED ( REF. 7 ) START THE VACUUM PUMP
BY PUSHING VAC BUTTON AND RELEASE THE HAND FROM THE CAP ONCE THE VACUUM LEVEL
IS KEEPING IT WITH ENOUGH SUCTION. CHECK THE VALUE ON VACUUM GAUGE ( REF. 9 )
AND BE SURE THAT A GOOD VACUUM SITUATION IS BETWEEN - 60 AND – 76 ( DEPENDING OF
THE ALTITUDE FROM SEA LEVEL ).
MIXER USE: DELICATE AND PRECISE OPERATIONS
ONCE THE VACUUM LEVEL HAS BEEN REACHED
SWITCH OFF THE VACUUM PUMP !
ALWAYS OPERATES IN THIS PROCESS STEP UNDER VACUUM BUT WITH THE PUMP OFF
TO AVOID ECCESSIVE BUBBLING ON THE MIXTURE.
TO TRANSFER THE EXACT WATER QUANTITY FROM THE DOSING TANK
TO THE MIXING CONTAINER PROCEED AS FOLLOW:
JUST REMEMBERING THE DRY POWDER QUANTITY LOADED,
KEEP ONE FINGER TO THE EXACT CORRESPONDANT LEVEL LINE ON THE STICKER
OF THE WATER DOSING TANK IN ORDER TO AVOID MISTAKES AND LOAD TOO MUCH WATER
OR LESS WATER IN THE MIXING CONTAINER.
a) OPEN TAP ( REF. 6 ) AND CLOSE IT IMMEDIATELY AS WATER LEVEL LINE ON DOSING
TANK WILL LOWERED TO THE FINGER INDICATING THE CORRESPONDENT VALUE OF
THE POWDER PREVIOUSLY LOADED. ( REFER TO PAGE 7 )
b) Start mixing operation ( PUSH MIX BUTTON ) we suggest to start initially slow and
adjust speed according to the density condition of the mixture.
c) Keep the vacuum level on the vacuum meter controlled not lower than - 55 / -60
d) During mixing operation, check the flask correspondence to the pouring hole and
eventually adjust the flask position by pushing SX or DX where ROTAZIONE
PIATTO is written on control panel.
e) Blade speed and rotation could be adjusted without problems during the machine
functions.