Inspection of outgoing emergency materials
Packing list of TK3 ground power supply system (M30 version)
5.1.2 Power-on inspection
① Whether the ground end start up normally.
② Whether the ground end display screen can display parameters normally.
③ Flight power supply test: whether the equipment can supply power to the
drone, and whether ML150 matrix light can be lit normally.
④ Whether the ground end can take up normally.
⑤ Observe whether each fan can rotate normally.
⑥ Whether the drone can take off normally.
TK3 ground end
Ground power connection cable
Detachable stand
TK3-M350 drone end
TK3-M350 Battery Plug
Insulating gloves
Hanging wire buckle
Product qualification certificate
Product instruction
1 unit
1 cable
4pcs
1pc
1pc
1 Pair
2 pcs
1pc
1pc
86