SiBE121021_C Pump Down Operation
Trial Operation and Field Settings 439
1. Pump Down Operation
Outline In order to protect the environment, be sure to conduct pump down operation when relocating or
disposing the unit.
Detail 1) Remove the valve caps from the liquid stop valve and the gas stop valve.
2) Carry out forced cooling operation.
3) After 5 to 10 minutes, close the liquid stop valve with a hexagonal wrench.
4) After 2 to 3 minutes, close the gas stop valve and stop the forced cooling operation.
Refer to page 440 for forced operation.
Gas stop valve
Close
Liquid stop valve
Valve caps
Hexagonal wrench
(R14566)

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Daikin Super Multi NX FFQ35B8V1B and is the answer not in the manual?

Daikin Super Multi NX FFQ35B8V1B Specifications

General IconGeneral
BrandDaikin
ModelSuper Multi NX FFQ35B8V1B
CategoryAir Conditioner
LanguageEnglish

Related product manuals