Installation Checklist
Following are the steps needed to install the Wheel Balancing Machine. Perform them in the order
shown.
☐ 1. Unpack and verify that all parts are accounted for and undamaged.
☐ 2. Review the installation Safety Rules.
☐ 3. Verify that there is a power source available at the installation location. Make arrangements for an
electrician, if required.
☐ 4. Make sure you have the necessary Tools.
☐ 5. Make sure there is adequate clearance around and above the DB-70.
☐ 6. Unpack the Components.
☐ 7. Connect the matcher to the Balancer shaft.
☐ 8. Install the tray and control panel.
☐ 9. Move the unit to its permanent Location.
☐ 10. Anchor the Unit.
☐ 11. Install the Tire Cover.
☐ 12. Connect to Power. This will require a
licensed Electrician
if you are converting to 220 VAC.
☐ 13. Test the Balancer. See Balancer Testing.