4.4.12
4.4.11
4.4.10
of
INDUSTRIAL PUMPS
www.debem.com

rev
CAUTION: danger of loss of the afxed ATEX or IECEX marking.
It is forbidden to use the pump with temperatures higher than those allowed and specied in the manual; if
exceeded, conformity with the afxed ATEX or IECEX marking is cancelled.
 If the pump is equipped with a STROKE COUNTER (to detect and/or view the number of pump cycles), provide
for the electrical connection.
 Always protect the pump from possible accidental blows and from contact with incompatible uids that can dam-
age it and/or react upon contact with it.
 If used for pumping ammable, aggressive, toxic or harmful uids for health and/or in installations in zone 1 - zone
21 - zone M2 and for pumping ammable uids (allowed by the marking), it is necessary to install an
adequate protection on the pump (for containment, collection and outow of the product in a safe area),
and a buzzer in case of spillage.
CAUTION: danger of pollution, contamination, injuries or, in extreme cases, death.
It is forbidden to install the pump in the absence of a suitable protection for containment with a collection
tank and outow in a safe area of ammable, aggressive or toxic liquids or with liquids that may represent
a health hazard.
The pneumatic circuit connection and the pump installation are thus completed.
4.5 CHECKS PRIOR TO COMMISSIONING
Depending on the type of application, the type of uid used, the installation/work environment, it is neces-
sary to afx appropriate indications and indicate the residual risk present near the pump.
Before commissioning the pump, in order to verify that the installation actually meets the intended oper-
ating conditions, it is essential to carry out the following checks with the pump running:
 With a pressure gauge positioned directly on the air inlet of the pump (downstream of all devices and ttings
installed on the supply line), check that the detected pressure does not have any pressure drops com-
pared to the reading on the pressure gauge of the lter of the pneumatic network supply line.
 With a pressure gauge directly on the delivery manifold of the pump, check that the actual pressure of the pumped
uid at the pump outlet is correct compared to the Technical data of the installed Model.
The pump is ready for commissioning.