Section 2 – Installation Qualification (IQ)
Initial Qualification and Requalification
The IQ protocols described below are dedicated to initial qualification and/or to requalification. Instal-
lation Qualification tests should be performed, 1) when the system is installed, 2) when the system is
moved to a new location, 3) prior to running OQ tests.
This section describes the procedure for receiving, unpacking, and installing a Series 4 AquaLab
Water Activity instrument.
The purchased AquaLab Water Activity instrument undergoing qualification is located at:
Company Name:
Department:
Address:
City: State:
Country:
Zip code/Postal Code:
Phone Number:
2.1 Equipment identification
Fill out this section after unpacking the AquaLab instrument and corresponding accessories.
4 4TE 4TEV 4TE DUO 4TEV DUO
Manufacturer: DECAGON DEVICES
Model Number:
Serial Number:
Decagon Devices Authorized Representative
Name:
Date:
Signature:
Initials:
2.2 Receiving and Unpacking
Verify that the external packaging was not damaged during shipment in a way that the internal package
content might be damaged.
External package condition Satisfactory Not Satisfactory
Remarks: N/A

Other manuals for Decagon Devices AquaLab 4TE

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Decagon Devices AquaLab 4TE and is the answer not in the manual?

Decagon Devices AquaLab 4TE Specifications

General IconGeneral
BrandDecagon Devices
ModelAquaLab 4TE
CategoryMeasuring Instruments
LanguageEnglish

Related product manuals