2 Getting Started With Your System
Before you begin, make sure the site where you intend to set up and use
the Storage Center has the following:
•
Standard power from an independent source or a rack power
distribution unit with a UPS.
•
Storage Center with the latest firmware, BIOS, and drivers. Contact
your supplier for the correct software versions.
Installation Overview
The installation process follows the general steps below. For detailed
information, refer to vendor documentation supplied with the equipment.
NOTE: The system is intended for restricted access location in
accordance with the National Electric Code, National Standards Institute
(ANSI/National Fire Protection Association (NFPA) 70).
CAUTION: If installed in a closed or multi-unit rack assembly, the
operating ambient temperature of the rack environment may be greater
than room ambient temperature. Therefore, consideration should be given
to installing the equipment in an environment compatible with the maximum
ambient temperature (Tma) specified by the manufacturer. For more
i
nformation, see "Technical Specifications" on page 7.
1
Assemble the rails following the safety instructions and the rack
installation instructions provided with your system.
2
Install network switches, as applicable.
3
Install the SC4020 chassis into the rack.
•
Always load the rack from the bottom up for weight stability.