CAIRplus Appendix
PR-2009-0096-GB • Subject to modifications • R8-10/2015 87
We recommend to keep account of all maintenance procedures in the log book even after the first two years of operation
have elapsed. It is under circumstances necessary to perform specified maintenance and cleaning procedures in reg-
ular intervals anyway.
Maintenance
frequency
Unit part
Checked
O.K.
not O.K.
Comment
Date Signature:
Month 18 following
commissioning
Heat Exchanger
Fan assembly
Refrigeration plant
Control
Panels
Filters
Condensate pan
Damper blades
Other components
Defects/damage was directly communicated to company: on (date):
Defect/damage was repaired by: on:
Month 21 following
commissioning
Heat Exchanger
Fan assembly
Refrigeration plant
Control
Panels
Filters
Condensate pan
Damper blades
Other components
Defects/damage was directly communicated to company: on (date):
Defect/damage was repaired by: on:
Month 24 following
commissioning
Heat Exchanger
Fan assembly
Refrigeration plant
Control
Panels
Filters
Condensate pan
Damper blades
Other components
Defects/damage was directly communicated to company: on (date):
Defect/damage was repaired by: on: