4.2 Preparation of the burner air intake for balanced flue operation mode
Evolution boilers come prepared from factory for operation by taking the intake air for the burner
from the room.
In case of choosing room sealed mode operation, with the evacuation of the combustion gases
through an outlet conduct and a independent external air intake, air intake for the burner must be
prepared following these instructions:
- Remove the top panel (1).
- Turn the air intake conduct (2) and take out the air intake terminal (3) por from the back (4).
- Tie air intake terminal (3) at the back (4) with two screws (5) (included in the documentation
bag).
- Remove the grid (6) (this won´t be used).
- Reattach the roof (1).